Task Summary export does not contain reference to VSO

  • 71Views
  • Last Post 07 July 2017
  • Topic Is Solved
0
votes
Frank posted this 31 January 2017

When a task is created from withing Visual Studio Online. The titile of the task is prefixed with the product backlog item id.

When this report is exported to as CSV file, this information is removed !

Order By: Standard | Newest | Votes
0
votes
Aleksandr Serdyuk posted this 07 February 2017

Actually it was never included.

0
votes
Frank posted this 08 February 2017

Can you add it to the export then ?

0
votes
Aleksandr Serdyuk posted this 08 February 2017

We'll think about it. TMetric integrates with a number of systems and that id is not always human readable. In such case you don't want it to be exported.

 

0
votes
Aleksandr Serdyuk posted this 07 July 2017

We've just released a TMetric update that allows exporting work item IDs.